6. Installation
6.1 Installation drawing
Fig. 22
Example of a typical arrangement
6.2 Installation requirements
6.2.1 Installation location
• The installation location must be free of vibrations.
• The installation location must be protected from rain, humidity,
condensation, direct sunlight and dust.
• The installation location must be sufficiently illuminated to
ensure safe handling of the system.
• The installation location must be in a solid building.
• Observe the permissible ambient conditions. See section
.
6.2.2 Foundation and space requirement
For the installation of the system, provide a solid concreted
surface, suitable for the weight and dimensions of the system.
Install the system on a horizontal foundation.
Maximum slope: 1:200
Make sure all components are always easily accessible for
operation and maintenance.
For details on weights, dimensions and space requirement, see
section
6.2.3 Water supply
The quality of the filtered water must comply with the
specifications in section
5.1.1 Water quality specification
. If the
pressure is insufficient, a booster pump is required. If the
produced sodium hypochlorite is dosed into drinking water, final
treated mains water should be used.
For flow rates see section
. The tables do not
include the water demand for water softener regeneration.
The water supply connections must comply with the respective
international standards, e.g. double non-return valves on the inlet
connection.
T
M
06
22
27
38
15
Pos. Description
1
Brine dosing station
2
SES with DC connections on the bottom or the top (here
on the top)
3
Rectifier in a separate room
4
One degassing and storage tank for each electrolyser
5
H2 dilution flow monitored via venturi nozzle and exhaust
air flow sensor
6
Installation room
The safety of the overall system is only guaranteed,
if the installation requirements are strictly adhered to.
All installation work must only be carried out by
qualified and authorised persons.
Separate the system from the power supply before
working on the system components and lines.
Wear the stipulated personal protective equipment.
Grundfos accepts no liability for any damage
resulting from incorrect installation.
Observe the maximum floor load.
The foundation must be based on a sufficiently
bearing ground.