Section 13: Flue System and Air Supply
Page 58
13.4 Prepare the Wall – Indoor installation only
If the oil boiler unit of the VortexAir Hybrid is to be installed indoors,
make the hole in the wall for the low level balanced flue system to
pass through, in the correct position as shown in Figure 9-10.
Dimension B given in Figure X-XX includes an extra 10mm
over the size of the terminal to provide clearance
NOTE
!
Table 13-9:
Flue hole dimensions
Model
Dimensions
A*
B**
C
VortexAir 15/21kW
1370
790
127
VortexAir 21/26kW
1370
790
127
* Includes an additional 100 mm for the anti-vibration mount/feet.
** Includes 600 mm clearance
Table 13-10:
Suitable wall thickness
To suit wall thickness
Minimum
Maximum*
EZ90 (no extension)
N/A
162
EZ90 + 225mm
197
387
EZ90 + 450mm
422
612
EZ90 + 950mm
922
1 112
* Includes 150 mm (rear) clearance between inner wall and rear of casing.
Refer to Section 2.7.2.
13.5 Fitting the Flue – Low Level (Yellow) balanced
flue system
Remove both the burner access door, the upper access panel
(above the door) and also the access panel on the front face of the
oil boiler casing.
Fit the vertical flue extension section (supplied with the VortexAir
Hybrid).
To do so, locate the threaded stud (at the bottom of the extension
section) into the threaded socket in the centre of the flue outlet (on
the top of the boiler heat exchanger). See Figure 9-11.
Figure 13-12:
Fitting the vertical flue extension section
Rotate the extension section to screw the stud into the socket
until the flange (at the bottom of the extension section) is firmly
compressing the circular neoprene gasket on the top of the heat
exchanger.
Depending on the location selected for the Hybrid boiler unit, either
inside or outside the building, remove and discard the circular
‘knock out’ section, as required.
•
For outdoor installation: Remove the ‘knock out’ from the end
face of the Hybrid boiler casing.
•
For indoor installation: Remove the ‘knock out’ from the rear
face of the Hybrid boiler casing.
Fit the boiler connection section
Unpack the flue kit and check the contents.
Take the boiler connector section and remove the self-tapping screw
holding the outer pipe and remove the outer pipe. See Figure 13-13.
Figure 13-13:
Removing the self-tapping screw
Figure 13-11:
Flue hole dimensions & position for low level system
Side wall
Rear wall
•
Содержание Aerona3 Series
Страница 57: ...Section 13 Flue System and Air Supply Page 57 Figure 13 8 Flue clearances...
Страница 77: ...Section 19 Spare Parts Page 77 Figure 19 4 15 21kW baffles Figure 19 5 21 26kW baffles...
Страница 84: ...Appendix A Page 84 Appendix A...
Страница 85: ...Appendix A Page 85...
Страница 86: ...Appendix A Page 86...
Страница 87: ...Appendix A Page 87...