Detector Tests
If the devices have been assigned to Zones (via the programming menus) then it is possible to test the detectors with
limited or no sounder operation.
Detector Tests by Zone
1.
Before starting clearing all faults, put the system into programming Mode and press SYSTEM RESET.
2.
In programming mode, select function 7-3 Sounders on Test Activation. This allows you to choose an audible
confirmation that a device has detected a fire. The audible confirmation consists of a 1 second period of sounder
operation.
3.
ALL SOUNDERS ON DETECTOR TEST activates the Panel’s Conventional and Loop Sounders.
4.
Now select function 7-4 Test Zones to select the Zones which will be tested.
5.
Exit programming mode, but DO NOT press SYSTEM RESET as this clears all test modes.
6.
In test mode, whenever a detector is activated the LED on that detector will be ON and the event will be reported
on the panel for 15 seconds. If selected, the sounders will also operate for 1 second.
7.
Pressing TEST (QUEUE REVIEW) will report the Zones that are in Test Mode.
Unassigned Detector Tests
1.
If the detectors have not been assigned to a Zone then they can only be tested in normal (Active) mode. Using
the programming menu, ensure the system is set to Active Mode, then exit programming mode and press
SYSTEM RESET.
2.
Carry out a fire test on each detector. Confirm the LED lights on the detector under test. Confirm that the fire is
reported correctly at the Panel (and any Repeaters). Confirm that the sounders operate.
3.
Note that sounders and detectors can be inhibited or delayed using the advanced features in the programming
menus. If the sounders do not operate as expected, first verify all the settings for the sounders and the device
under test.
At this point you may program the more advanced features of the system. The basics usually involve assigning text labels
to the devices and Zones.
Global Devices Tests
For this test please access the menu “7-1 Device Count, Type & Value” and verify if the device is fitted.
For specific testing please refer to the device manual.
WRAPPING UP INSTALLATION AND COMMISSIONING
Once you have completed the mentioned steps, do not forget to carry out the following:
1.
Connect the batteries to the Panel as described in the Installation section of this manual.
2.
Test that the battery monitoring is functional by temporarily removing the blue wire between the
batteries. After a few seconds the fault should be reported on the Panel (Battery Fault Message Test
explained further).
3.
When the blue wires are reconnected, pressing SYSTEM RESET should clear the fault report.
4.
Test that the primary supply monitoring is functional and that the battery system works. Switch off the AC
supply to each power supply unit in the Panel. After a few seconds the fault should be reported on the
Panel (Power Failure Test explained further).
5.
Reconnect the AC supplies and press SYSTEM RESET.
6.
Confirm that the system is in Active Mode - the SYSTEM ON LED is permanently lit.
NODE+ / Installation & Commission Manual / © GFE 220331
25
Содержание NODE+
Страница 45: ...EN54 13 SPECIFICATIONS Devices with EN54 13 approval NODE Installation Commission Manual GFE 220331 45 ...
Страница 48: ...EN54 and CE SPECIFICATIONS NODE Installation Commission Manual GFE 220331 48 ...
Страница 49: ...DECLARATION OF CE CONFORMITY NODE Installation Commission Manual GFE 220331 49 ...