STEP 14: Align the two desk height keyholes with the groove in the panel’s horizontal,
desk height frame extrusion.
STEP 15: Insert two rectangular anchor nuts with supplied screws through the
keyholes in the Power Pole.
Tighten the screws, while ensuring the Power Pole is vertical.
STEP 16: Align the two bottom keyholes with the groove in the panel’s bottom
frame extrusion.
STEP 17: Insert two rectangular anchor nuts with supplied screws through keyholes
in the the aluminum Power Pole.
STEP 18: With the Power Pole now in its fi nal position, mark the ceiling tile, cut a
tight outline hole and reinstall the ceiling tile.
STEP 19: Pull the Electrical Feed conduit up one side of the Power Pole partition.
Secure the conduit to the junction box strain relief fi tting.
STEP 20: Run the data cables up the other side of the partitioned Power Pole and
snap on the Power Pole Cover. It consists of a shorter section (below the
work surface) and a longer section (between the work surface and the
ceiling).
STEP 21: Install the Ceiling Bezel and secure it with two supplied screws.
Check the complete installation of the electrical components and connect to
the building power supply through the adjacent ceiling tile.
WARNING: It is recommended that the installation of the electrical harness
be made under the supervision of a licensed electrician in accordance with
applicable codes and regulations.
SPECIAL NOTE: Always determine that the harness is electrically connected
to the only one power supply.