Chapter 6
OPERATING THE DRILLING RIG
1
Chapter 6
OPERATING THE DRILLING RIG
6.1 Getting Started
6.1.1
Positioning on the ground of the drilling machine
The machine must operate on a flat surface.
The ground contact of crawlers must be uniform. For this purpose, the dozer
blade can be used for leveling the ground when present small irregularities.
It can also be used to lift the machine to make it work on a flat surface (up to
a slope of 4%).
6.1.2
Configuration of the mast, tracks and dozer blade.
The mast should be brought to the maximum height subject to space
available. This operation is obtained by operating the manipulator B. This
allows the tool, during rising, to reach the maximum height. In this way, by
rotating the turret, the download of the soil extracted from the hole can be
made laterally. The track width of the undercarriage must be brought to the
maximum width and the blade (extended)) resting on the ground to increase
the stability.
6.1.3
Testing the winch DOWN limit switch
When laying the tool on the ground, check the rope of the main winch: it
should not loosen further (i.e., the winch should not turn) even if you
insistently operate the kelly bar
’s descent control. If the rope continues to
unwind, check whether the limit switch has been disabled. If the limit switch is
not disabled contact the service department. You can continue to work