Innova 2100-IQ, 3100/3100-IQ, 4100/4100-IQ Cardiovascular Imaging System Pre-Installation Manual
GE Healthcare
Direction 5314528-2-1EN, Revision 1
17 PIST0021 - US Fluoro UPS and PDB connection
17.1 Personnel Requirements
Required Persons
Preliminary Reqs
Procedure
Finalization
1
Not Applicable
1 hour
Not Applicable
17.2 Preliminary Requirements
17.2.1 Tools and Test Equipment
Item
Qty
Effectivity
Part#
Manufacturer
Standard Service
Engineer’s toolkit
1
-
-
-
17.2.2 Required Conditions
Condition
Reference
Effectivity
The PDB is already installed
-
-
Power cables are as follows: (1) From
PDB to UPS rectifier input = 4x6
AWG recommended (4x3 AWG max)
(3ph + PE). (2) Bypass = 5x8 AWG
recommended (5x3 AWG max)(3ph +
N+PE). (3) From UPS output to PDB = 5x8
AWG recommended (5x3 AWG max)(3ph
+ N+PE)..
-
-
Cable sizing shall follow local
requirements.
-
-
Power cable Mechanical Terminals Torque
Specification: < 3 Nm / < 27 lb.in for 20
AWG to 3 AWG.
-
-
Check the UPS shipping date marked
on the packaging label. Commissioning
of the UPS must be performed within 3
months after that date.
-
-