Page
12
Chapter 1 — Installation and Initial Setup
Chilled mirror setup
The GE General Eastern HumiLab is shipped with the chilled
mirror sensor (1111H-SR) and temperature probe (T-100) already
installed.
Initialize the
dew point
sensor
Although it was initialized at the factory, the dew point sensor
bridge should be initialized again to compensate for any change
during shipment. This is accomplished by cleaning and balancing
the sensor as described below. Figure 7, shows the location of the
switches and LEDs on the front panel. Chapter 2 contains a
complete description of the operating procedures.
1. Plug the A/C power cord into a wall socket.
Figure 5 — Front Panel Controls
Содержание HumiLab
Страница 43: ...Chapter 5 Maintenance and Troubleshooting Page 39 Figure 13 Mirror Check and Mirror Sensor Balancing Procedure ...
Страница 75: ...Appendix D Humidity Equations and Conversion Charts Page 71 Figure 16 Graphical Conversion Chart ...
Страница 76: ...Page 72 Appendix D Humidity Equations and Conversion Figure 17 Psychrometric Chart ...
Страница 80: ...Page 76 Appendix E Warranty information and return ...