17
Step 4: Set tank
Step 5: Fill tank with fresh water to
Low water level mark in all 3
chambers.
Note: Start with center chamber and
alternate chambers while filling for
evenly balanced fill.
Water
To assure tank water tightness, check in 24 hours to be sure that the water level has not dropped.
Contact your distributor or Fuji Clean USA if water level has dropped.
Use 4-point lifting lugs. Carefully
lower and set tank.
Check that tank is level to 1/8” per 2
feet, (10mm per 2 meter or 1/200),
fore and aft as well as side to side.
Step 3: Set pre-cast concrete or
pour concrete base.
H-20 and HS-20 load needs
concrete base.
Bearing power of soil should be
8.7PSI or more.
Pre-cast concrete base
Check the concrete is level to 1/8” per 2 feet
(10mm per 2 meter or 1/200),
(fore and aft as well as side to side).
Содержание CE6KG
Страница 29: ...29 Step 12 continued Rebar arrangement details ...
Страница 33: ...33 M Control Panel Wiring Diagram p 1 ...
Страница 34: ...34 M Control Panel Wiring Diagram p 2 ...
Страница 37: ... A Control Panel Wiring Diagram p 2 37 ...