4. Commissioning
4−9
Festo P.BE−CPASC−EN en 0412b
4.3
Testing the valves and the valve−actuator combination
Please note
Before commissioning the CPA−SC valve terminal, note the
specifications on medium, see chapter Installation",
section Pilot control of the valve solenoid coils (pilot air)".
Proceed as follows when commissioning the CPA−SC valve
terminal:
Commissioning variants Activity
Preliminary check of the
pneumatic tubing
Checking the valve−actuator
combination by means of the manual
override
Complete commissioning of
the complete system
Installing and connecting the
complete system.
Program control by PLC/industrial PC
Tab.4/3:
Variants of commissioning
The commissioning of the pneumatic components by means
of the manual override is described below.
Содержание Smart cubic CPA-SC Series
Страница 2: ......
Страница 4: ...Contents and general instructions II Festo P BE CPASC EN en 0412b...
Страница 16: ...Contents and general instructions XIV Festo P BE CPASC EN en 0412b...
Страница 17: ...Summary of components 1 1 Festo P BE CPASC EN en 0412b Chapter 1...
Страница 41: ...Fitting 2 1 Festo P BE CPASC EN en 0412b Chapter 2...
Страница 53: ...Installation 3 1 Festo P BE CPASC EN en 0412b Chapter 3...
Страница 81: ...Commissioning 4 1 Festo P BE CPASC EN en 0412b Chapter 4...
Страница 98: ...4 Commissioning 4 18 Festo P BE CPASC EN en 0412b...
Страница 99: ...Maintenance and conversion 5 1 Festo P BE CPASC EN en 0412b Chapter 5...
Страница 112: ...5 Maintenance and conversion 5 14 Festo P BE CPASC EN en 0412b...
Страница 113: ...Technical appendix A 1 Festo P BE CPASC EN en 0412b Appendix A...
Страница 129: ...Index B 1 Festo P BE CPASC EN en 0412b Appendix B...
Страница 130: ...B Index B 2 Festo P BE CPASC EN en 0412b Contents B Index B 1...
Страница 136: ...B Index B 8 Festo P BE CPASC EN en 0412b W Weights A 4...