7. Preparations for commissioning
118
Festo.P.BE-CMMS-ST-G2-HW-EN
1008NH
7.4
Connecting the CMMS-ST stepping motor
controller to the power supply
Connecting the
stepping motor
controller
1.
Make sure that the power supply is switched off.
2.
Insert the PHOENIX plug into the socket [X9] on the device.
3.
Connect the 24 V connection to a suitable power pack.
4.
Connect the power supply unit.
5.
Check all plug connectors once again.
7.5
Connecting a PC
Connecting a PC
1.
Insert the D-sub plug of the serial interface cable into the socket
for the serial interface of the PC and secure the locking screws.
2.
Insert the D-sub plug of the serial interface cable into socket
[X5] RS232/COM for the CMMS-ST stepping motor controller
and secure the locking screws.
3.
Check all plug connectors once again.
7.6
Checking readiness for operation
Checking readiness
to operate
1.
Make sure that the controller enable switch is switched off.
2.
Switch on the power supplies for all devices. The READY LED on
the front of the device should now light up.
If the READY LED does not light up, there is a fault. If the seven
segment display shows a number sequence, this is an error
message. You must rectify the cause of the message. If this is the
case, see chapter
8.2 Error messages (page 122). If no display
lights up on the device, proceed as follows:
No display lights up 1.
Switch off the supply voltage.
2.
Wait for one minute to allow the intermediate circuit to
discharge.
3.
Check all connecting cables.
4.
Check that the 24 V control voltage is functional.
5.
Switch on the supply voltage again.