Installation Site Requirements
Depending upon the cabling used, you need to provide 7.5 to 10 cm (3 to 4 in.) of clearance on the
switch I/O port side of the SSA switch.
See
Environmental Guidelines for ExtremeSwitching Products
for environmental guidelines relating to
the SSA switch installation.
The installation site must be within reach of the network cabling and must meet the requirements listed
below:
•
Appropriate grounded power receptacles must be located within 2 meters (7 feet) of the site.
•
A temperature of between 5°C (41°F) and 40°C (104°F) must be maintained at the installation site
with fluctuations of less than 10°C (18°F) per hour.
Caution
To ensure proper ventilation and prevent overheating, leave a minimum clearance space of 5.1
cm (2.0 in.) at the front and rear of the device.
Precaución: Para asegurar una buena ventilación y evitar que el sistema se sobrecaliente, deje
un espacio mìnimo de 5.1 cm (2 pulgadas) con respecto el anverso y reverso del aparato.
Unpacking the SSA Switch
Unpack the SSA switch as follows:
1 Open the box and remove the packing material protecting the SSA switch.
Save the shipping box and materials in case the unit must be reshipped.
2 Remove and set aside the RJ45-to-DB9 converter, anti-static wrist strap, adhesive feet (for flat
surface placement), and power cord retention clips.
The SSA switch
does not
include screws for attaching the SSA switch to rack posts.
3 Verify the contents of the carton as listed in
.
Table 3: Contents of the SSA Switch Carton
Quantity
Item
1
SSA chassis
1
RJ45 management cable
1
RJ45-to-DB9 converter
1
Anti-static wrist strap
4
Adhesive rubber feet
2
Power cord retention clips
1
SSA Quick Reference
4 Inspect the SSA switch for any signs of physical damage.
If there are any signs of damage, do not install the SSA switch; instead,
Installation
S-Series Stand Alone (SSA) Switch Hardware Installation Guide
12