UPS System Installation
4-28
Power Xpert
TM
9395 550/275 UPS (225–550 kVA) Installation and Operation Manual
164201716—Rev 8
www.eaton.com/powerquality
Installation Checklist
o
All packing materials and restraints have been removed from each cabinet.
o
Each cabinet in the UPS system is placed in its installed location.
o
A cabinet grounding/mounting kit is installed between any cabinets that are bolted together.
o
All conduits and cables are properly routed to the UPS and any ancillary cabinets.
o
All power cables are properly sized and terminated.
o
Battery cables are terminated on E4 (+) and E5 (–).
o
Battery aux contact signal wiring is connected from the UPS to the battery disconnect.
o
Battery shunt trip signal wiring is connected from the UPS to the battery disconnect. (OPTIONAL)
o
LAN drops are installed.
o
All LAN connections have been completed.
o
A ground conductor is properly installed.
o
Air conditioning equipment is installed and operating correctly.
o
The area around the installed UPS system is clean and dust–free. (It is recommended that the UPS be installed on a level
floor suitable for computer or electronic equipment.)
o
Adequate workspace exists around the UPS and other cabinets.
o
Adequate lighting is provided around all UPS equipment.
o
A 120 Vac service outlet is located within 7.5 meters (25 feet) of the UPS equipment.
o
The REPO device is mounted in its installed location and its wiring is terminated inside the UPS cabinet.
o
The normally-closed (NC) Emergency Power-off contact (pins 1 and 2 on TB1) is jumpered if not used.
o
Alarm relays and building alarms are wired appropriately. (OPTIONAL)
o
A remote battery disconnect control is mounted in its installed location and its wiring is terminated inside the UPS and
battery cabinet. (OPTIONAL)
o
Accessories are mounted in installed locations and wiring is terminated inside the UPS cabinet. (OPTIONAL)
o
The debris shield covering the UPS cabinet ventilation grill is removed.
o
Startup and operational checks are performed by an authorized Eaton Customer Service Engineer.
Содержание Power Xpert 9395 550/275
Страница 1: ...Power Xpert 9395 UPS 550 275 UPS 225 550 kVA Installation and Operation Manual...
Страница 2: ......
Страница 3: ...Power Xpert 9395 UPS 550 275 UPS 225 550 kVA Installation and Operation Manual...
Страница 27: ...Section 1 Installation...