4.
Installation instruction
Use the water pipe to connect the water supply inlet and the tap water source, then
connect the electricity. Press the power on button, then the machine will work
automatically, after a few seconds the machine will start to atomize automatically.
When install the pipe, the pipe line must be arranged reasonably, the interface
must be sealed to prevent leakage of gas or water, please also make the pipe line
in leveled to ensure the fog pressure smoothly so as to avoid the machine damaged
by any blocking. In order to avoid the fog hole water beard down, the outlet hole
of the fog should be located in the position of the PVC pipe cross section level up
30 degrees or so, the best diameter of the out put fog hole are 20 to 30mm , the
spacing between the outlet hole of the fog is depends on the length of the pipe(for
example, if the single pipe length is 12m, the spacing should be with 15-20cm).
Please also block off the end of the pipe so as to avoid water accumulation in the
pipeline, the level height of the ends should be adjustable slightly above the mist
side for the principle, condensate can return.
In addition, do not reduce the pipe diameter or make to much turning. See Fig 7.
When install the machine, the pipe height should be higher than 1 meter but lower
than 3 meter, the horizontal length according to the following table please.
Fog volume
Length of single
pipe
Fog volume
Length of single
pipe
3KG
L≤10m
6KG
L≤15m