60708-151
2080-10
RECEIVING THE GENERATOR
The generator set will generally be shipped by a commercial
‘common freight carrier’. Routing is determined by the bulk, size,
and a means available to unload the generator at the receiving
end. WINPOWER recommends units that are shipped by
common carrier be delivered to a commercial dock to allow the
Generator Set to be unloaded in a safe, efficient manner and to
minimize handling damage to the unit.
Locate the packing slip on the side of the crate or request it from
the truck driver. When receiving the unit take special care in
examining the unit for damage during shipment. Avoid signing for
the equipment until a full visual assessment and inventory have
been made. Verify that you have received the right equipment
and the proper amount by matching up the equipment to the
packing list.
UNPACKING INSTRUCTIONS:
When unpacking the generator set, be sure to inspect it carefully
for freight loss or damage. If loss or damage is noted at the time
of delivery, require that the person making the delivery make note
of the loss or damage on the freight bill, or affix his signature
under the consignee’s memo of the loss or damage. Contact the
carrier for claim procedures.
When loss or damage is noted after delivery, segregate the
damaged material, and contact the carrier for claim procedures.
“Concealed Damage” is understood to mean damage to the
contents of a package which is not in evidence at the time of
delivery by the carrier, but which is discovered later. The carrier
or carriers are responsible for merchandise lost or damaged
in transit. The title to goods rests with the consignee when
generators are shipped fob factory, and only the consignee can
legally file a claim.
***** CAUTION ****
EQUIPMENT DAMAGE -
These units are shipped with oil,
and a 50/50 mix of coolant. Be sure to check all fluid
levels before operating. See engine manufacturer’s
instruction manual for recommended oil requirements
before initial starting.
UNPACKING:
(Not recommended until the unit is on-site)
1. Carefully remove the crate.
2. After inspecting the engine-generator for external physical
damage, locate and check the following items packed with
the unit.
a. Owner’s operators manual.
b. Engine manufacturer’s instruction manual.
c. Battery hold-down brackets & hardware.
d. Unit components or accessory items shipped loose
for on-site installation.
e. Optional accessories.
3. Remove main frame hold down bolts.
4. Unit can now be lifted from shipping rails.
LIFTING THE GENERATOR SET
NOTICE - Personal Injury
To prevent injury to persons or equipment, observe the
following guidelines when lifting the generator:
Due to the different designs, configurations, options, weights,
site conditions, and available material handling equipment,
specific lifting instructions are not provided for each individual
generator set model. General guidelines provided are applicable
to the entire standby generator line. It is the responsibility of the
installing party to follow the lifting equipment’s operators manual
to prevent injury to personnel and damage to the generator.
Smaller Generator Sets may not require use of overhead lifting
equipment and may be placed on the pad with basic material
handling equipment, i.e. a forklift.
CAUTION
: - Do not attempt to lift the generator set by the means
of the lifting eyes on the engine or generator end.
These lifting points are only for use during the manufacturing
process and are designed for lifting of the individual Generator
Set component.
***************
***** WARNING ****
***************
NEVER - attempt to lift the fuel tank while filled with fuel.
Sloshing of the fuel can cause a shift in the balance of the
fuel tank, making for a DANGEROUS, unbalanced lifting load.
If the generator was shipped on the fuel tank, use the lifting
points located on the fuel tank to move the entire Generator
Set into place. DO NOT place fuel in the tank prior to lifting.
INSTALLATION
***************
***** WARNING ****
***************
PERSONAL INJURY - Before proceeding with the installation,
be sure the engine control is in the “stop” position. Before
proceeding with the installation, be sure the Generator MLCB
(Main Line Circuit Breaker) is in the ‘OFF’ position and the
unit starting battery is disconnected.
GENERAL INFORMATION
This series of engine/generator sets are designed and built
as open power unit, meaning no weather protection has been
provided. These unit must be installed inside of an enclosure that
will provide proper protection from the elements.
Содержание WINPOWER DE20I4
Страница 10: ...60708 151 2080 10 CONTROL BOX AC WIRING WARNING THESE GENERATORS ARE WIRED WITH A FLOATING NEUTRAL...
Страница 15: ...2080 10 60708 151 13 DE30 OUTLINE DRAWING DE20 OUTLINE DRAWING...
Страница 16: ...60708 151 2080 10 14 DE45 DE60 OUTLINE DRAWING...
Страница 17: ...2080 10 60708 151 15 DE20 DE30 DC SCHEMATIC FOR DSE702...
Страница 18: ...60708 151 2080 10 16 DE45 DE65 DC SCHEMATIC FOR DSE702...
Страница 19: ...2080 10 60708 151 17 START CONTROL PANEL ENGINE WIRING HARNESS DE20 DE30 KEY START SCHMATIC...
Страница 20: ...60708 151 2080 10 18 START CONTROL PANEL ENGINE WIRING HARNESS DE45 DE65 KEY START SCHMATIC...
Страница 21: ...2080 10 60708 151 19 THREE PHASE AC WIRING HIGH AND LOW WYE...
Страница 22: ...60708 151 2080 10 20 THREE PHASE AC WIRING DELTA SINGLE PHASE AC WIRING...
Страница 24: ...225 S Cordova ave Le Center MN 56057 507 357 6831 www winpowerinc com 60708 151 2080 10...