![Dover Anthony Complete 101 Series Скачать руководство пользователя страница 13](http://html1.mh-extra.com/html/dover/anthony-complete-101-series/anthony-complete-101-series_installation-manual_2524816013.webp)
Complete 101 Series Installation Manual
99-25517-I001 July 2022 Rev. B
12 |
P a g e w w w . a n t h o n y i n t l . c o m
Section 2 – Standard Walk-In Line-Up Frame Installation
Tools Required
Refer to
“Equipment List & Tools”
in Section 1 for a complete list of all equipment, tools, materials, and other things needed for installation. If
the Frames are not installed upon arrival, they should be protected from the environmental conditions, and ensure storage of the product
indoors at a normal room temperature of 75°F or less, do not store outside, weather can damage the frame and cause issues such as plastic
deformation.
PROTECTIVE GEAR NOTICE
Protective Gloves– Potential risk of injury to your hands, protective gloves required when
performing this, and any other associated tasks.
Footwear Protective – Potential risk of injury to your feet, wearing protective footwear is
required when performing this and any other associated tasks.
Frame Unpacking
Before beginning installation follow the instructions below to unpack the frames for shipping crates safely and effectively.
1.
Locate the factory-painted instructions on the crate which read “OPEN ON THIS SIDE” (they are painted with red ink).
2.
Carefully, place the crate flat on the floor with the “OPEN ON THIS SIDE” facing up.
3.
Remove all screws from the top and bottom wood planks to remove, followed by the center plank.
4.
Carefully, pull the frame from the create and prepare to install it in the case.
Figure 2.1: Frame Crate
NOTICE
Note –
When you have multiple frames, please refer to the “Continuous Lineup Frame
Installation” instructions in this section. Depending on your configuration you will have two
(2) to three (3) different frames (Right Flanged, Continuous, and Left Flanged).