5 Commissioning / Shut-down Procedure
OM Hydraulic Aggregate, Version 1.0 01/2013
35
5
Commissioning / Shut-down Procedure
5.1 Commissioning
/
Operation
We call your attention expressly to the fact that the conversion and the
hydraulic installation of the device may only be carried out by trained per-
sonnel with a profound mechanical and hydraulic knowledge!
(
2.8 Safety Instructions for Commissioning)
Before commissioning, ensure that the device is in a secure position.
During operation, the device's own vibrations may cause it to move so it should
be fastened down appropriately.
During operation, the device must not be covered.
When using a hydraulic aggregate with a pneumatic motor, the shut-off valve
(ball cock) should be opened slowly.
A hydraulically driven device may only be connected to the hydraulic aggregate
when switched off.
The control valve of the hydraulically driven device must be in the zero position.
The control valve of the
hydraulically driven device
must be in the zero position
in order to start the motor/engine.
First connect the return and then the feed.
Before commissioning, always check the oil level. Place the device on a level
surface.
Oil level:
Minimum level:
the sight glass is 1/2 filled with oil.
Maximum level:
the sight glass is 2/3 filled with oil.
Содержание BP2
Страница 1: ...English 6000 0509 00 Product Manual Hydraulic Aggregate 2 Translation of the original product manual...
Страница 20: ...Appendix A Signature List 14 IM Hydraulic Aggregate 2 Version 1 0 01 2013...
Страница 21: ...English 6000 0509 00 Operation Manual Hydraulic Aggregate 2 Translation of the original operation manual...
Страница 77: ...10 Technical Data OM Hydraulic Aggregate Version 1 0 01 2013 53 Empty page...