SiE33-003
Refrigerant Piping
Installation Manual
143
6.4
Leak Test and Vacuum Drying
The units were checked for leaks by the manufacturer.
Confirm that the valves are firmly closed before pressure test or vacuuming.
Air Tight Test and
Vacuum Drying
Air tight test: Make sure to use nitrogen gas.
Pressurize the liquid and gas pipes to 3.2MPa (do not pressurize more than 3.2MPa). If the pressure
does not drop within 24 hours, the system passes the test. If the pressure drops, check where the
nitrogen leaks from.
Vacuum drying: Use a vacuum pump which can evacuate to –100.7kPa (5Torr, –755mmHg).
1. Evacuate the system from the liquid and gas pipes by using a vacuum pump for more than 2 hours and
bring the system to –100.7kPa. After keeping the system under that condition for more than 1 hour,
check if the vacuum gauge rises or not. If it rises, the system may either contain moisture inside or have
leaks.
2. Following should be executed if there is a possibility of moisture remaining inside the pipe (if piping
work is carried out during the raining season or over a long period of time rainwater may enter the pipe
during work).
After evacuating the system for 2 hours, pressurize the system to 0.05MPa (vacuum break) with
nitrogen gas and evacuate the system again using the vacuum pump for 1 hour to –100.7kPa (vacuum
drying). If the system cannot be evacuated to –100.7kPa within 2 hours, repeat the operation of vacuum
break and vacuum drying.
Then, after leaving the system in vacuum for 1 hour, confirm that the vacuum gauge does not rise.
When conducting an airtightness test
1. RXYP (Main unit)
2. RXEP (Sub unit)
3. Gas side valve
4. Liquid side valve
5. Liquid side
6. Gas side
7. Connecting valve
(Service port)
8. Indoor units
9. Regulator
10.Gauge manifold
11.Nitrogen
1. RXYP (Main unit)
2. RXEP (Sub unit)
3. Gas side valve
4. Liquid side valve
5. Liquid side
6. Gas side
7. Connecting valve
(Service port)
8. Indoor units
9. Regulator
10.Gauge manifold
11.Nitrogen
When vacuum drying
1. RXYP (Main unit)
2. RXEP (Sub unit)
3. Gas side valve
4. Liquid side valve
5. Liquid side
6. Gas side
7. Connecting valve
(Service port)
8. Indoor units
9. Gauge manifold
10.Vacuum pump
1. RXYP (Main unit)
2. RXEP (Sub unit)
3. Gas side valve
4. Liquid side valve
5. Liquid side
6. Gas side
7. Connecting valve
(Service port)
8. Indoor units
9. Gauge manifold
10.Vacuum pump
RSXYP16,18,20
3
4
9
10
5
2
1
7
6
8
11
Fig. 16-1
(V0864)
RSXYP24,26,28,30
3
4
9
10
2
5
1
7
6
8
11
Fig. 16-3
(V0866)
3
4
9
2
1
5
7
6
8
10
RSXYP16,18,20
Fig. 16-2
(V0865)
3
4
9
5
2
1
7
6
8
10
RSXYP24,26,28,30
Fig. 16-4
(V0867)
Si33-003.book Page 143 Monday, June 25, 2001 9:06 AM
Все каталоги и инструкции здесь:
http
:
//splitoff.ru/tehn-doc.html