Test Operation
SiE 00-07
76
Test Operation R-407C PLUS Series
1. Test Operation
1.1
Procedure and Outline
The operation sequence is the most important thing for test operation. Follow the following outline.
1.1.1
Check The Following Before Turning Power On.
1.1.2
Turn Power On.
Refer to Setting Modes on P81
Mistaken power wiring, loose screws
Mistaken control transmission wiring, loose screws
Piping size, presence of thermal insulation
Measurement of main power circuit insulation
Addition or replenishment of refrigerant as needed
Fully open respective stop valves on liquid, gas.
Use a 500V megar-tester.
Be sure to record addition or replenishment.
(VF128)
Turn on outdoor unit power.
Set various selectable modes on outdoor unit PC board.
Turn on indoor unit power.
Be sure to turn the power on 6 hours before
starting operation in order to supply
electricity to the crankcase heater.
For field settings, see setting modes.
(VF129)
Содержание FXYBP20K7V1
Страница 1: ...System R 407C PLUS Series Service Manual SiE 00 07 ...
Страница 11: ...Introduction SiE 00 07 x ...
Страница 17: ...Product Outline SiE 00 07 6 General Information R 407C PLUS Series ...
Страница 41: ...Specifications SiE 00 07 30 Specifications R 407C PLUS Series ...
Страница 90: ...SiE 00 07 Test Operation Test Operation R 407C PLUS Series 79 1 3 Outdoor Unit PC Board Ass y Outdoor Unit ...
Страница 119: ...Test Operation SiE 00 07 108 Test Operation R 407C PLUS Series ...
Страница 132: ...SiE 00 07 Troubleshooting by Remote Controller Troubleshooting R 407C PLUS Series 121 ...