The valve will not
shift from cooling to
heating
The following list explains what the possible causes could be:
■
Check the electrical circuit. If there is no voltage to the coil, repair it.
■
Check the coil. If it is defective, replace it.
■
Check the refrigerant charge. If the charge is low, repair it and recharge the system. If the pressure
differential is too high, re check the system.
■
Check the following operation conditions to find the cause of the malfunction. The numbers in the
columns refer to the numbers in the drawing on the previous page:
1
2
3
4
5
6
Description
Hot
Cool
Cool as
in
column
2
Hot as
in
column
1
Temperature
of valve
body
Hot
The pilot valve works correctly.
There is dirt in one bleed hole. To
resolve:
1
Deenergize the solenoid.
2
Raise the head pressure.
3
Reenergize the solenoid to
loosen the dirt.
4
If unsuccessful, remove the
valve and wash it out. Check
on air before reinstalling. If
there is still no movement,
replace the valve, add a new
strainer to the discharge tube
and mount the valve
horizontally.
The piston cup head leaks. To
resolve:
1
Stop the unit.
2
After pressure equalization,
restart with energized
solenoid.
3
If the valve shifts, reattempt
with the compressor on. If
there is no reversal, replace
the valve.
Hot
Cool
Cool as
in
column
2
Hot as
in
column
1
Temperature
of valve
body
Temperature
of valve
body
The pilot tubes are clogged. To
resolve:
1
Raise the head pressure.
2
Operate the solenoid to free
the dirt.
3
If there is still no shift, replace
the valve.
Hot
Cool
Cool as
in
column
2
Hot as
in
column
1
Hot
Hot
Both parts of pilot are still open.
To resolve:
1
Raise the head pressure.
2
Operate the solenoid to free
the partially clogged port.
3
If there is still no shift, replace
the valve.
Warm
Cool
Cool as
in
column
2
Hot as
in
column
1
Temperature
of valve
body
Warm
The compressor is defective.
Содержание EUWA/Y5-30HB/C(Z)
Страница 2: ......
Страница 8: ...Introduction ESIE98 06A vi 3 1 4 5...
Страница 10: ...ESIE98 06A 1 2 Part 1 System Outline 3 1 1 4 5...
Страница 28: ...General Outline ESIE98 06A 1 20 Part 1 System Outline 3 1 1 4 5...
Страница 36: ...Piping Layout ESIE98 06A 1 28 Part 1 System Outline 3 1 1 4 5...
Страница 52: ...ESIE98 06A Wiring Layout Part 1 System Outline 1 44...
Страница 58: ...ESIE98 06A 2 2 Part 2 Functional Description 3 1 2 4 5...
Страница 80: ...The Controller for the EUWA Y5 10HB Z Chillers ESIE98 06A 2 24 Part 2 Functional Description 3 1 2 4 5...
Страница 98: ...The Controller for the EUWA Y15 30HC Z Chillers ESIE98 06A 2 42 Part 2 Functional Description 3 1 2 4 5...
Страница 100: ...ESIE98 06A 3 2 Part 3 Troubleshooting 3 1 3 4 5...
Страница 134: ...Troubleshooting ESIE98 06A 3 36 Part 3 Troubleshooting 3 1 3 4 5...
Страница 136: ...ESIE98 06A 4 2 Part 4 Commissioning and Test Run 3 1 4 5...
Страница 142: ...Pre Test Run Checks ESIE98 06A 4 8 Part 4 Commissioning and Test Run 3 1 4 5...
Страница 146: ...ESIE98 06A 5 2 Part 5 Maintenance 3 1 5 4...