12
|
Commissioning
Installer reference guide
230
EBLA04~E23V3 + EDLA04~E23V3
Daikin Altherma 3 M
4P685228-1A – 2022.05
To perform an actuator test run
Conditions:
Make sure all operation is disabled. Go to [C]:
Operation
and turn off
Space heating/cooling
and
Tank
operation.
1
Set the user permission level to Installer. See
—
2
Go to [A.2]:
Commissioning
>
Actuator test run
.
3
Select a test from the list.
Example:
Pump
.
4
Select
OK
to confirm.
Result:
The actuator test run starts. It stops automatically when
ready (±30 min).
To stop the test run manually:
—
1
In the menu, go to
Stop test run
.
2
Select
OK
to confirm.
Possible actuator test runs
▪
Booster heater
test
▪
Backup heater 1
test
▪
Backup heater 2
test
▪
Pump
test
INFORMATION
Make sure that all air is purged before executing the test run. Also avoid disturbances
in the water circuit during the test run.
▪
Diverter valve
test (3-way valve for switching between space heating and
tank heating)
▪
Bivalent signal
test
▪
Alarm output
test
▪
C/H signal
test
▪
DHW pump
test
12.4.5 Underfloor heating screed dryout
About underfloor heating screed dryout
Purpose
The underfloor heating (UFH) screed dryout function is used for drying out the
screed of an underfloor heating system during the construction of the building.
NOTICE
The installer is responsible for:
▪
contacting the screed manufacturer for the maximum allowed water
temperature, to avoid cracking the screed,
▪
programming the underfloor heating screed dryout schedule according to the
initial heating instructions of the screed manufacturer,
▪
checking the proper functioning of the setup on a regular basis,
▪
performing the correct program complying with the type of the used screed.
Содержание EBLA04E2V3
Страница 280: ...14 14 ...
Страница 281: ......
Страница 282: ......
Страница 283: ......
Страница 284: ...4P685228 1A 2022 05 Copyright 2022 Daikin Verantwortung für Energie und Umwelt ...