Installation and Test Operation
FM4 S6E2H-Series Starter Kit Guide, Doc. No. 002-11387 Rev. **
18
2.3.2 Test Procedure Explanation
This section explains the test procedure. This test procedure is based on the Serial Port Viewer.
The user has to key-in the test procedure number displayed on the menu to run the test
procedures and then press the
Enter
key on the PC to complete the test. The firmware on the
board will run the test procedure and display the results. There are eight test procedures. A short
description of each test procedure is given below:
Red LED (RGB LED) Test
: This procedure will test whether red LED works normally.
Key in
1
to run the test procedure and the red LED will blink. Then press the
Enter
key
on the PC to complete the test and
TESTED
will be displayed next to the test.
Figure 2-11: Red LED Test
Green LED (RGB LED) Test
: This procedure will test whether green LED works
normally. Key in
2
to run the test procedure and the green LED will blink. Then press the
Enter
key on the PC to complete the test and
TESTED
will be displayed in the console.
Figure 2-12: Green LED Test