Visit www.commscope.com for complete specifications on all the products listed
Bulletin # 7693902 Rev. L
Technical Publication
5
Required:
For field installed hoisting grips be
sure to install provided Tie Wrap to
the base of the hoisting grip before
applying tension to the line.
!
Clevis
Steel cable or
rope hoist line
Hoisting
grip
Maximum 60 m
(200 ft)
between
hoisting
grips
Hoisting Considerations: RRU End
Install tie back ropes
and tie wraps to
keep power and fiber
together during hoisting
If the structure does not allow the
breakout to fit through access ports due
to space limitations skip to next page
WARNING:
If the hoisting grip is pre-installed
the installation crew MUST follow
steps 6 and 7 printed on back of
the hoisting grip packaging before
hoisting the cable. This will entail
removing any slack in the grip and
installing zip ties at base of the grip.
!
1 m (3 ft)