Film (or 5.2 oz) Cover Installation with Ridge Vent
9. Take the remaining material and use it to cover the other side of the frame. Repeat steps to pull cover onto frame.
10. Secure cover to 111613Z144 rail attached to frame. Open vent to gain access to the double channel as needed.
Using the proper lifts, work from inside the frame to secure cover to the u-channel attached to the frame. (See
dashed line below.) Work down each end rafter to side run of double channel. Stretch cover and secure to 102197
u-channel. Trim excess material from installed cover. Trim a few inches below the u-channel.
Step 9
Step 10
Step 10
Step 10
Step 9
Photo above shows 102198 spring
wire used to secure cover material
to the u-channel attached to the
end rafter.
Always fully install wire in channel.
Wear eye protection when installing
spring!
11. Continue with the next procedure.