6-11
Cisco RF Gateway 10 Hardware Installation Guide
OL-16264-04
Chapter 6 Cabling the Cisco RFGW-10 UEQAM
Installing or Replacing the Cables in the UCH2
Table 6-3
RF Switch Universal Cable Holder Reference Color Coding
To replace cables or install new cables in an UCH2, complete the following steps:
Step 1
Use the T-10 TORX driver tool to loosen the lock bar on the side where the cable will be installed (See
Figure 6-9
Using the T-10 TORX Driver Tool to Loosen the UCH2 Lock Bar
Step 2
Use a flat-head screwdriver as a lever to slide open the lock bar (if needed). (See
RF Switch Line Card Port
Cable Color
RF Switch User-Defined
RFSW Slot 12
Red
RFSW Slot 11
White
RFSW Slot 10
Blue
RFSW Slot 9
Green
RFSW Slot 8
Yellow
RFSW Slot 7
Violet
RFSW Slot 6
Orange
RFSW Slot 5
Black
RFSW Slot 4
Gray
RFSW Slot 3
Brown
155822
Содержание RFGW-10
Страница 8: ...R E V I E W D R A F T C I S C O C O N F I D E N T I A L Contents viii Book Title OL 16264 04 ...
Страница 14: ...6 Cisco RF Gateway 10 Hardware Installation Guide OL 16264 04 ...
Страница 106: ...4 4 Cisco RF Gateway 10 Hardware Installation Guide OL 16264 04 Chapter 4 Thermal Management Environmental Monitoring ...