Page 12 | 1-800-343-9463
CCM9000
101017
SPLIT SYSTEM CHECKLIST
In order to activate the warranty for this product, the information here must be complete and accurate. Any
incorrect or omitted information will result in a return trip by the installing technician at their cost.
Note: All readings need to be taken while the compressor is running.
DATA RECORDINGS
Line Set Information
A.
Line set length:
B.
Suction line OD:
C.
Liquid Line OD:
Sub Cooling
A.
Measure head pressure at liquid line king valve . Convert pressure to temp using conversion chart .
B.
Temp of liquid line at king valve:
C.
Complete sub cooling calculation: A – B =
Superheat Master
A.
Measure suction pressure at the suction line service valve, convert to temp .
B.
Measure the temperature of the suction line at the outlet of the evaporator .
C.
Complete superheat calculation: A – B =
NOTE:
There may be a need to adjust the TXV to get the correct superheat levels .
Bottle Probe
A.
Install probe in bottle of warm water to keep system operating .
Temperature Differential at the Evaporator
A.
Measure return air and supply air temperatures at the evaporator to ensure adequate cooling of air in cellar .
Voltage and Amp Draw
A.
Measure voltage to compressor and amp draw .
Charging the System
A.
Fill system until bubbles dissipate from sight glass .
NOTE: Be careful not to overcharge the system.
Compressor Temperature
A.
Measure temperature at bottom of compressor .
NOTE: Cool temp may indicate liquid in the compressor.
Condensation Drain Test
A.
Pour water into the drain pan to assure it drains properly .
Superheat Slave
A.
Measure suction pressure at the suction line service valve, convert to temp .
B.
Measure the temperature of the suction line at the outlet of the evaporator .
C.
Complete superheat calculation: A – B =
NOTE:
There may be a need to adjust the TXV to get the correct superheat levels .