Configuring the Module in a DIGITAL MultiSwitch 900 4-23
[6] Downline Upgrade
If the Process Does not Complete
If the process does not complete as described in Stage 3, take one of the following
actions:
Stage
Description
4
The module resets, runs self-test, and then begins executing the
new firmware image.
This stage normally takes 1 minute to complete.
The following states indicate that this stage is in progress:
•
Module status – not functional or manageable.
•
Module cannot respond to management requests.
•
LED display –
—
Power LED is on.
—
Module OK LED is off.
—
Port State LEDs flash indicating various subroutines are running
(standard self-test pattern).
•
Hub Manager display –
This message is normal and indicates the module is not manageable.
If...
Then...
Because...
The module
loses power.
Contact your
representative.
The firmware image is
corrupted.
The Port State
LEDs 4 and 5
do not light.
Check that the load host
is operational.
The load did not succeed.
MS FE Hub 924TX