Commissioning (for engineers only)
Logamatic SC40 - Technical specifications are subject to change without prior notice.
46
6
6
Commissioning (for engineers only)
V
Follow the instructions in the technical documentation for the solar pumping station, the collec-
tors and the solar storage cylinder when commissioning the solar thermal system.
V
Only put the solar thermal system into operation when all pumps and valves are in proper working
order.
Perform the following steps in connection with the solar pumping station:
V
Check the system is clear of air.
V
Check and adjust the flow rate.
V
Enter the controller settings in the commissioning and maintenance report (
Æ
installation and
operating instructions for the solar pumping station).
Warning:
risk of damage to pump if run dry.
V
Make sure that the solar thermal circuit is filled with solar fluid (
Æ
installation and
maintenance instructions for solar pumping station).
Warning:
commissioning when there is frozen water or vaporisation in the solar ther-
mal system can damage the system.
V
Shield the collectors from direct sunlight during commissioning.
V
Do not commission the solar thermal system at sub-zero temperatures.
Warning:
setting the wrong operating mode can damage the system.
In order to prevent undesirable starting of the pump when the power supply is con-
nected, the controller is factory-set to
Always off
mode.
V
For normal operation, set the controller to
Auto
. (
Æ