5.3.4
Check combustion air/flue gas system and hose
connections
z
Check combustion air/flue gas system for blockages.
5.3.5
Replacing the UBA
z
Disconnect system from power supply by removing main
fuse or power connection plug.
z
Swivel the UBA to one side and pull the four-pin plug of the
mains power switch out at the back of the UBA.
z
Disconnect all plug-in cables. Note the position of each
plug-in cable.
z
Loosen the three screws on the UBA and remove it.
z
Remove mains power switch and fit to new UBA.
z
Screw the replacement UBA into position.
z
Reconnect all plug-in cables to their correct sockets.
z
Fit the casing.
z
Connect system to mains power supply.
z
Move mains power switch to “