3-9. Connecting the cords
1. Gently tilt back the machine head.
2. Pass the cord bundle through the hole
in the work table.
3. Loosen the two screws (1), and then
open the cord presser plate (2) in the
direction of the arrow and pass the
cord bundle through the opening
together with the following cords.
•
Two-pedal foot switch (3)
•
Operation panel (Do not pass the
ground wires through the hole.)
•
Solenoid valve assembly
4. Securely connect the connectors as
indicated in the table below.
<Main P.C. board>
NOTE:
•
Check that the connector is facing the correct
way, and then insert it firmly until it locks into
place.
•
Secure the cables with cable ties and cord
clamps, while being careful not to pull on the
connector.
*1:
Be sure to make the ground connection.
(Refer to "3-10. Connecting the ground wire".)
*2:
Only applicable to -484 SF specifications.
Connector
Connection location on
main P.C. board
Cord clamp
X pulse motor encoder 5-pin white
P20 (X-ENC)
(3)
Y pulse motor encoder 5-pin blue
P4 (Y-ENC)
(3)
Work clamp pulse motor encoder 5-pin black
*2
P5 (P-ENC)
(3)
Foot switch 10-pin
P6 (FOOT)
(3)
Operation panel 8-pin
P1 (PANEL)
(3)
Machine head switch 3-pin
P9 (HEAD-SW)
(4)
Home position sensor assembly 12-pin
P8 (SENSOR1)
(4)
STOP switch 6-pin
P13 (HEAD)
(4)
Valve harness 12-pin
P12 (AIR1)
(4)
Valve harness 5-pin
P26 (AIR3)
(4)
Programmer relay harness 8-pin
P7 (PRG)
(3)
Solenoid selection harness 4-pin
P3 (CUTTER)
-
Thread trimming cylinder sensor harness 16-pin
P23 (EX-IN1)
(4)
Lock the cord
clamp securely.
(Continued on next page)