Assembly – Assembling the door handle
Push the stove door closed and secure it by attaching the handle and turning it clockwise
until you achieve a gas tight seal.
Assembly - Gas Connection & Pressure Testing
A minimum 15mm-diameter gas supply pipe must be used to within 1 metre of the
installation with the final connection to the stove to be completed with the suitable 8mm
semi-rigid gas pipe. The 8mm pipe should be connected to the inlet of the gas valve using
the nut and 8mm olive provided. Support the control whilst finally tightening the supply
pipe.
The gas supply connection to the appliance is located at the right hand side rear of the
stove. The connection requires an 8mm-diameter semi-rigid pipe, not more than 1 meter in
length. This connection is a compression fitting, sealant should never be used (as this can
potentially cause a blockage).
Pressure Testing
Always make sure that there is adequate gas pressure and volume to the stove. The
relevant pressures are on the ID plate on the gas control knob.
1.
For natural gas, this is 20mbar
measured at the inlet connection to the stove with
the appliance in the full rate position.
2. Ensure that the gas pressure to the stove is maintained when it is operating at the
same time as other appliances in the building and that a suitable pressure gauge is
used i.e. a manometer.
Any service call as a result of incorrect gas pressure
will be chargeable.
Ventilation (GB only)
The gas stove is rated at less than 7kw and therefore does not normally require additional
ventilation in the room (BS5871
– part II).