Test Procedures – 7
7–39
Time Delay Accuracy Test
TEST SETTINGS:
Forward Power
Flow Magnitude
3.0 pu
Time Delay
30 Cycles
10. Press ENTER. The SELECT FUNCTION LED
should turn on and the unit should display
VOLTAGE RELAY
VOLT freq curr powr
C
11. Turn the knob clockwise until the unit displays
POWER RELAY
volt freq curr POWR
C
12. Press ENTER until the unit displays
DELAY FORWARD POWER
1 Cycle
13. Turn the knob clockwise until the unit displays
DELAY FORWARD POWER
30 Cycles
14. Press ENTER once and then EXIT until the
unit displays
BECKWITH ELECTRIC CO.
M-0420
15. Increase the input current to 16.00 A and
start timing. The unit should trip after 30
cycles time delay.
16. The 32 DIRECTIONAL OVERPOWER LED
should turn on and the unit should rotate
displays
-TRGT- 06/22/93 10:19:12
Trip# = 30
-TRGT- 06/22/93 10:19:12
FORWARD OVERPOWER
17. Set the input current to 0.00 A.
18. Press TARGET RESET/LAMP TEST. The
32 DIRECTIONAL OVERPOWER LED should
turn off. The unit should display
BECKWITH ELECTRIC CO.
M-0420
—END—
32F
DIRECTIONAL POWER, FORWARD POWER, 3-PHASE (CONT.)
Содержание M-0420
Страница 56: ...M 0420 Instruction Book 3 4 This Page Intentionally Left Blank ...
Страница 92: ...M 0420 Instruction Book 5 28 This Page Left Intentionally Blank ...
Страница 156: ...A 8 M 0420 Instruction Book This Page Intentionally Left Blank ...
Страница 160: ...B 4 M 0420 Instruction Book This Page Intentionally Left Blank ...
Страница 164: ...C 4 M 0420 Instruction Book This Page Intentionally Left Blank ...
Страница 165: ...D 1 Board Interconnections Appendix D D Board Interconnections Figure D 1 M 0420 Board Interconnections ...
Страница 166: ...D 2 M 0420 Instruction Book This Page Intentionally Left Blank ...
Страница 174: ...E 8 M 0420 Instruction Book This Page Intentionally Left Blank ...