21
Part No. 6-847703-00 Rev. C00
Installation
Initial Power-Up and Operational Testing
• Reserve header master valve is turned
fully counterclockwise(open).
• Both red "EMPTY" lights on front of
manifold and both red lights on front of
power supply (“RESERVE IN USE” and
“RESERVE LOW”) are illuminated.
• If connected to a master alarm panel,
"SECONDARY SUPPLY", “RESERVE IN
USE”, and “RESERVE LOW” alarms are
activated.
3. Close 3/4" source shut-off valve.
4. Slowly open one cylinder on high-pressure
reserve header assembly.
1. Release two latches on sides of manifold
cover (one on each side). Remove cover as
shown in Figure 17.
2. Verify following: (Refer to Figure 18 for
component location).
• Both manifold master valves are turned
fully counterclockwise (open)
• All four manifold line regulator isolation
valves are open (handles horizontal).
• Power supply cable has been attached to
connector on bottom of manifold .
Figure 17