23
Part No. 6-847703-00 Rev. C00
19. Record pressure readings of manifold’s left
and right contents gauges.
20. Record pressure reading of reserve header
contents gauge.
21 Close liquid container on left side of manifold.
22. Close high-pressure cylinder on right side of
manifold and reserve header.
23. Wait 15 minutes.
24. Compare current readings of manifold left and
right gauges and reserve header contents
gauge to those recorded in step 19 and 20. If
there is a noticeable pressure change on
either gauge, perform leak testing described in
the next section.
25. Reinstall manifold cover.
26. Slowly open all liquid containers on manifold’s
left bank, high-pressure cylinders on
manifold’s right bank and high-pressure
cylinders on reserve header.
27. Open 3/4" source shut-off valve.
Installation