background image

14

24, the overcurrent protection is enabled by
undervoltage units and works as long as 60FL
logic does not block the trip path. In Fig. 25 the
potential is taken from bus VTs, rather than unit
VTs, so the scheme will function even if the VT
fuses were removed during unit maintenance.

In Fig. 24 the terminal voltage will be zero prior
to energization, so the 27 and 81U relay contacts
will be closed to energize the timer (62). The
instantaneous overcurrent relay (50) trip circuit is
established after timer 62 operates. Upon
inadvertent generator energization, the under-
voltage and underfrequency relay contacts may
open up due to the sudden application of nominal
voltage and frequency, but the delayed dropout
of 62 allows relay 50 to initiate tripping. The use
of a 60FL function or two 27 relays on separate
VT circuits avoids tripping for a VT fuse failure.
Alternatively, a fuse loss detection or voltage-
balance relay (60FL) could be used in conjunc-
tion with a single 27 relay to block tripping.

FIGURE 24. INADVERTENT ENERGIZATION
PROTECTION USING INSTANTANEOUS
OVERCURRENT RELAY (50).

In Fig. 24 the 5 sec pickup delay on timer 62
prevents tripping for external disturbances that
allow dropout of the 27 relays. The 27 relays
should be set at 85% voltage (below the operat-

ing level under emergency conditions). The Fig.
25 scheme could be employed where protection
independent of the plant is desired. In this case
the 67 relays would be placed in the switchyard
rather than in the control room. While directional
overcurrent relay (67) should be delayed to ride
through synchronizing surges, it can still provide
fast tripping for generator faults, since the 67
relays need not be coordinated with external
protection. Fig. 25 shows the operating range for
phase A current (Ia) with respect to phase B to C
voltage (V

BC

). This range is fixed by the 60

degree characteristic angle and the ±45 degree
limits set on the operating zone.

FIGURE 25. BE1-67 DIRECTIONAL OVERCURRENT
RELAYS DETECT INADVERTENT ENERGIZATION.

Negative Sequence Protection

Negative sequence stator currents, caused by
fault or load unbalance, induce double-
frequency currents into the rotor that may
eventually overheat elements not designed to be
subjected to such currents. Series unbalances,
such as untransposed transmission lines,
produce some negative-sequence current (I

2

)

flow. The most serious series unbalance is an
open phase, such as an open breaker pole. ANSI
C50.13-1977 specifies a continuous I

2

 withstand

of 5 to 10% of rated current, depending upon the
size and design of the generator. These values
can be exceeded with an open phase on a
heavily-loaded generator. The Basler
BE1-GPS100, BE1-951, BE1-1051, or BE1-46N
relay protects against this condition, providing
negative sequence inverse-time protection
shaped to match the short-time withstand
capability of the generator should a protracted

Содержание BE1-1051

Страница 1: ...GeneratorProtection ApplicationGuide...

Страница 2: ...ign of protective relaying systems He worked for Consolidated Edison Company for ten years as a System Engineer He has served as a private consultant since 1982 Updates and additions performed by vari...

Страница 3: ...it is rather expected that a 500kW 480V standby reciprocating engine will have less protection than a 400MW base load steam turbine unit One possible common dividing point is that the extra CTs neede...

Страница 4: ...ral VFG in Fig 1 Assuming an impedancegroundedgeneratorwhere Z0 SOURCE and ZN ZWINDING the current level is directly proportional to the distance of the point from the generator neutral Fig 1 a so a f...

Страница 5: ...rcuit or setting the relay fairly insensitively FIGURE 2 GROUND FAULT RELAYING GENERATOR LOW IMPEDANCE GROUNDING The neutral CT should be selected to produce a secondary current of at least 5A for a s...

Страница 6: ...gh rejection of fundamental frequency voltage FIGURE 6 GROUND FAULT NEAR GENERATOR NEUTRAL REDUCES THIRD HARMONIC VOLTAGE IN GENERATOR NEUTRAL DROPPING OUT 27 3N The 27 3N performs a valuable monitori...

Страница 7: ...ult as seen by the generator neutral shift sensing relay 59N leading to a generator trip Alternatively assume that the VT corner e g phase A has been grounded If phase B or C fault to ground the fault...

Страница 8: ...2 100 5 from the neutral When feeder cables are connected to the gen erator bus the additional capacitance dictates a much lower level of grounding resistance than achieved with a unit connected case...

Страница 9: ...hout pre loading For example assuming a pre fault 1pu rated load at 30 degree lag at one second the 3 phase fault value would be 2 4 times rated rather than 1 75 timesrated 1 30 1 75 90 2 4 69 Under t...

Страница 10: ...edapproach inhibits operation until the voltage drops below a preset voltage It should be set to function below about 80 of rated voltage with a current pickup of about 50 of generator rated Since the...

Страница 11: ...imes tap CDS220 or 0 4A 87G is representa tive of a recommended setting for a moderate mismatch in CT quality and burden Fig 13 also shows 51V relays to back up the 87G and external relays and breaker...

Страница 12: ...nchroniz ing when the generator is initially slower than the system Since motoring can occur during a large reactive power flow the real power component needs to be measured at low power factors The B...

Страница 13: ...y a mho circle centered about the X axis offset from the R axis by X d 2 Two zones sometimes are used a high speed zone and a time delayed zone FIG 19 LOSS OF EXCITATION USING IMPEDANCE RELAY With com...

Страница 14: ...r during a fault To prevent a 60FL from being declared during loss of station power it may be necessary to allow a 3 phase 60F to be declared only when some low level of load current exists FIGURE 22...

Страница 15: ...ach set point may be set to recognize either over frequency or underfrequency Multiple frequency set points are available in the BE1 81O U BE1 GPS100 BE1 951 and BE1 1051 Another common need for frequ...

Страница 16: ...ld be employed where protection independent of the plant is desired In this case the 67 relays would be placed in the switchyard rather than in the control room While directional overcurrent relay 67...

Страница 17: ...reaker depending on the type of fault that is detected For instance if the generator is protected by a 51V and an 87G and only the 51V trips it may be assumed that the fault is external to the generat...

Страница 18: ...EXAMPLE OF BARE MINIMUM PROTECTION LOW IMPEDANCE GROUNDING Fig 30 shows the suggested minimum protection with low resistance grounding It includes differential protection which provides fast selectiv...

Страница 19: ...ssive generator reactive absorption Ther mal relay 49 protects against stator overheating due to protracted heavy reactive power demands and loss of generator cooling Even if the excitation system is...

Страница 20: ...voltage balancerelay 60 field ground relay 64F frequency relay 81 and the 27 50 62 relay combination for inadvertent energization protection Relay 51GN provides a second means of detecting stator gro...

Страница 21: ...ures 34 through 37 show the BE1 GPS100 and BE1 CDS220 applied to generator protection Due to logic complexity full details are not shown Details of these applica tions may be found in the respective i...

Страница 22: ...20 FIGURE 35 BE1 GPS100 APPLIED TO HIGH IMPEDANCE GROUNDED GENERATOR HI_Z_GND PREPROGRAMMED LOGIC SEE INSTRUCTION MANUAL FOR LOGIC DETAILS...

Страница 23: ...FIGURE 36 BE1 CDS220 APPLIED TO GENERATOR FOR 87 PHASE 87 NEUTRAL AND 51 PHASE NEUTRAL GROUND AND NEGATIVE SEQUENCE 21...

Страница 24: ...s typical settings for use as a starting point in the setting determi nation procedure The proper settings are heavily influenced by the specifics of each application Typical settings are also used as...

Страница 25: ...urrent 49 20 StatorTemperature RTD Lower 95 C upper 105 C 50 87 12 Differentialviaflux PU 10 INOM or less if 1A relay may be used summationCTs 50 27 IE 24 InadvertentEnergization 50 0 5A 10 INOM Overc...

Страница 26: ...75 100 INOM GEN Definite Time 0 1 0 25 sec InadvertentEnergization Inst 200 INOM GEN 81 21 Over underfrequency Generator protection 57 62Hz 0 5s Island detection 59 61Hz 0 1s 87G 13 GeneratorPhase BE1...

Страница 27: ...9 59 X X X X X X 59N 27 3N 59N 59P 4 4 4 60FL 60 X X X 67IE 67 X X 81 81O U 81O U X X X X X 87G 87G X 87N 67N 87UD 87T X 1 50 51G Indicates a relay that monitors a ground CT source 2 50 51N Indicates...

Страница 28: ...54 2341 Fax 1 618 654 2351 BaslerElectricInternational P A E Les Pins 67319 Wasselonne Cedex FRANCE Phone 33 3 88 87 1010 Fax 33 3 88 87 0808 If you have any questions or need additionalinformation pl...

Отзывы: