Page 20 - INDeX Configuration
Ins
Complete INDeX Configuration.
1. Close off the INDeX cabinets.
2. Mount the INDeX Media Gateway and the IP Office modules in their final
location.
3. Connect the Expansion Link Cassette(s) to the INDeX Media Gateway using
Link Cable(s). Ensure that the Link Cables are connected to
both
the INDeX
cabinet earth and the INDeX Media Gateway earth points. Refer to page 28
for details.
4. For the IP Office modules, ensure that the require trunk interfaces and the
optional integral modules have been fitted.
5. Connect the IP Office module Expansion Ports to the INDeX Media Gateway
Expansion ports. Where IP Office Expansion modules are to be used, also
connect the IP Office module Expansion Ports to these Expansion modules.
6. Proceed with initial programming of the INDeX Media Gateway (see page 26).
Closing Off the INDeX Cabinet(s)
You must follow the steps below in order to maintain the EMC compliance of the
INDeX system.
To close off a cabinet :
a. Ensure that each cassette displays just the single green lamp.
b. Check that each cable to the cassettes is clearly labelled and identified.
c. Slide the cabinet grille plate back into the base of the cabinet. Ensure that the
cables all exit the cabinet through the proper cable exit points.
d. Secure the grille plate using the 2 screws previously removed at the start of
installation.
e. Adjust the cable clamp provided at the cable exit point.
f. Hook the front cover back onto the cabinet and secure the two captive cover
screws.
g. Check that none of the cabinet ventilation grills have been blocked.
Page 20 - Installing a New System
Installation Manual
38DHB0002UKGA Issue 1 (12/05/2004)
INDeX Media Gateway