MAN - BBR2S - REV: Original | E. Operation
The BBR2S’s system status lights, located at the bottom right of the screen, indicate whether or not a component is
ready for testing.
•
Red = the component requires standardization
•
Yellow = the component requires verification
•
Green = the component is ready for testing
The SPECIMEN NAME is any text you wish to make it. It is stored with the run data and printed on the report. This
allows you to keep track of which test data or report you are looking at. Be sure you set this BEFORE you run a test
for it to be included in the report.
The TEST NOTES button will bring up a dialog to allow you to enter any note you wish to keep with this test run.
They are stored with the run data and printed with the report. Be sure you write these BEFORE you run a test for
them to be included on the report.
If the BBR2S was sitting idle and the loading shaft was free hanging for more than one hour, place the non-
compliant beam on the specimen support, then manually exercise the load cell. To do this, place 100 gram of weight
on the weight pan and remove it, allowing three or four seconds between loading and unloading. Repeat this at least
four times, allowing three or four seconds between each time.
Load Setup
1. Load the non-compliant beam on the specimen supports.
2. The load control switch is located on the front of the BBR2S. Make sure the switch has been set to ZERO before
proceeding. (Figure E.12).
3. Adjust the zero regulator until the loading shaft contacts the non-compliant beam with a minimal force of 35 ±10
mN.