10.1.2 Start-up
•
Starting
(see
§
"3.2 Commissioning the heat pump", page 41
).
OK
Non conforming
Push in the installation's general circuit breaker (outdoor unit power supply)
2 hours before the tests => Compressor preheating.
Push in the on/off switch => Few seconds' initialisation.
Operation of the heating circulator
The outdoor unit starts after 4 min.
Configure Time, Date and Heating circuit, DHW hourly programmes if different from the default values.
Configure the hydraulic circuit (parameter 5700): Preset
10
Set the heating slope (720 and 1020).
Adjust the max start value (741 and 1041)
•
Checks on the outdoor unit
OK
Non conforming
Value
Operation of the fans, compressor.
Intensity measurement.
After a few minutes, measure the difference in air T°.
Condensation and evaporation pressure / temperature check.
• Checks on the hydraulic module
OK
Non conforming
Value
After 15 minutes' operation.
Difference in primary water T°.
DHW priority (directional valve switchover).
Heating operation, boiler reading, etc..
•
Regulation
(see "
§
3.3 Configuration of the sensor/central ambient unit"3.5, page 44 and/or 3.6, page 44
OK
Non conforming
Configuration, operations, checks.
Carry out the hourly programming for the heating periods (500 to 516 / 520 to 536).
Set the values for the heating circuits if different from the default values (710 - 714 ; 1010-1014).
Set the DHW values (1610-1612), if different from the default values.
Value display.
Usage explanations.
• Checks on the gas exchanger
(see
§
"3.3 Starting the gas generator
to check the combustion", page 42
).
OK
Non conforming
Value
Combustion check at 100 % (10 % < CO
2
< 11 %).
Combustion check at 0 % (9.5 % < CO
2
< 10.5 %).
The heat pump is ready to operate!
Installation and commissioning instructions "1485 - EN"
- 75 -
Heat pump alféa hybrid duo gas
Содержание 024200
Страница 45: ... ...
Страница 61: ... Installation and commissioning instructions 1485 EN 61 Heat pump alféa hybrid duo gas ...
Страница 78: ... ...
Страница 79: ... ...