Commissioning
With the first initiation of the control unit basic settings and tests are carried out. By entering the
plant size all important parameters are preset. However, we recommend, after commissioning to
enter “settings” and check the parameters again.
In the Service Mode you also have subsequently the opportunity to make changes.
Use the ↑↓-keys to select the desired language for the menus and display
and press OK. Available are English, German, French, Spanish, Romanian,
Polish, Italian.
With the input of the service code it is ensured that the commissioning is
carried out by a speciakist. Enter the 6 - digit code number using ↑ ↓ and
OK
.
Enter the data for date (display = dd.mm.yyyy) and time (display =
hh:mm:ss). Warning: the date of commissioning cannot be changed
later.
This is important for the correct entries in the logbook!
Use the ↑↓-keys to select the type of plant and confirm with
OK
.
Use the ↑↓-keys to select the PT size of the plant and confirm with
OK
.
Important for the correct preset parameters!
Enter the serial number which is located on the AQUAMAX
®
frame (BASIC /
CLASSIC / PRO G ) or inside the outdoor cabinet or on the mounting plate of
the control (PRO XL). Not the serial number of the control unit!
Please make sure to enter the serial number right justified.
With the confirmation of “new plant” to suppress sludge recirculation for the
duration of run-in phase (preset to 180 days for BASIC, CLASSIC and PRO
G).
Click
OK
to start the test run (with ↑↓
OK
and you can cancel the operation
and exit the menu item). Here all active outputs are sequentially switched ON
for about 5 seconds. Error messages are generated by current consumption
outside the preset current limits.
Furthermore, function and allocation of the float switches will verify.
Test run can be restarted by moving any float switch.
In the case of wrong settings, the commissioning may finally restart by
entering “no”. Confirm the correct entries with
OK.