Chapter 3: Configuration and commissioning
2X Series Installation Manual
77
Test/disable timeout
Configures a timeout value (in minutes) for zone
test and disablement operations for the local control
panel. See “Zone test/disable timeout” on page 78
for more information. [1]
060/000 [2]
[1] This feature is not compliant with EN 54-2.
[2] Default 060/000 corresponds to 60 minutes test timeout and no disable timeout.
To change the configuration:
1. Select Field setup from the Main menu, and then Zone configuration.
2. Select General config.
3. Make the required configuration changes.
4. Press F4 (Enter), and then press F1 (Back).
5. Press F1 (Save), F3 (Apply), F4 (Discard), or F2 (Exit).
Remember to apply saved settings from the Main menu.
Initial zone
The initial zone defines the starting point of the fire alarm control panel zone
range. The remaining zones for the corresponding control panel follow
sequentially, as shown in the table below.
Table 39: Initial zones
Control panel
Initial zone
Remaining zones
One-loop control panel
1
2 to 64
One-loop control panel
200
201 to 263
Two-loop control panel
1
2 to 128
Two-loop control panel
520
521 to 647
For repeater panels without a zone board, the initial zone value is not used as
the panel has no zones. The repeater panel displays zone events of the panels
being repeated.
First zone indicator LED
The first zone indicator LED defines the zone number for the first LED (top left)
for an installed zone indicator board. The remaining zones for the corresponding
control panel follow sequentially, as shown in Table 40 below.
The initial zone range is as follows:
• Between 01 and 9960 for a 40-zone indicator board
• Between 01 and 9980 for a 20-zone indicator board
• Between 01 and 9976 for a 24-zone indicator board
Содержание 2X Series
Страница 1: ...2X Series Installation Manual P N 501 405003 1 31 REV 03 10 ISS 07NOV13 ...
Страница 6: ...iv 2X Series Installation Manual ...
Страница 20: ...Chapter 1 Introduction 14 2X Series Installation Manual ...
Страница 110: ...Chapter 3 Configuration and commissioning 104 2X Series Installation Manual ...
Страница 121: ...Chapter 5 Technical specifications 2X Series Installation Manual 115 Figure 27 Large cabinet dimensions and views ...
Страница 122: ...Chapter 5 Technical specifications 116 2X Series Installation Manual Figure 28 Small cabinet dimensions and views ...
Страница 140: ......