71
HELIX™ Manual
(P/N 26291)
Chapter 4: System Installation
Rev A (February 2018)
HELIX™ PCU
Fire Suppression System
For multiple pressure switch circuit installations (See Figure 4.8.4b):
1.
Begin at the last Pressure Switch, located farthest from the STRIKE Control Unit. Route either
end of the Pressure Switch Extension Cable (P/N 24703
-
XX or 21539
-
XX) to the next Pressure
Switch.
See Section 3.6.5 for all requirements for conduit, junction boxes, and outdoor
installations. If conduit is used, it must be 3/4” conduit.
Any excess length in the
extension cable must be coiled and stored.
Do not cut, pinch, crush, or chafe any electrical
wiring or connectors during installation.
2.
Repeat Step 1 for any remaining Agent Cylinders and Pressure Switches in series.
3.
At the first Pressure Switch, route the blunt cut end of the Pressure Switch Lead Cable (P/N
24414
-
XX) to the inside of the STRIKE Control Unit enclosure through the selected knockout.
This circuit may be routed through the same conduit as the actuation circuit if used. Any
excess length in the cable should be pulled into the STRIKE Control Unit enclosure.
Do not
cut, pinch, crush, or chafe any electrical wiring or connectors during installation.
4.
At the last Pressure Switch, connect the Pressure Switch connectors to the extension cable
connectors [(M) to (F); (F) to (M)].
5.
At the remaining Pressure Switches, connect the (6) connectors as shown, creating a circuit
loop [(M) to (F) x 3].
6.
Termination of the Pressure Switch Lead Cable to the STRIKE Control Unit is performed in
Section 4.9.
Ensure the Pressure Switches and associated cables are fully installed and
connected before proceeding to prevent any fault conditions.
(M)
PRESSURE SWITCH
LEAD CABLE
(P/N 24414
-
XX)
ROUTING
DIRECTION
(SECOND PRESSURE SWITCH)
(FIRST PRESSURE SWITCH)
INTO STRIKE
CONTROL UNIT
ENCLOSURE
SEE FIGURE 4.8.4a
PRESSURE SWITCH
EXTENSION CABLE
(P/N 24703
-
XX or
21539
-
XX)
Figure 4.8.4b
(F)
(M)
(F)
(M)
CONNECT x 2
(F)
(M)
(F)
CONNECT x 3
(M)
(F)
JUNCTION BOX & CONDUIT
(AS REQUIRED)
JUNCTION BOX
& CONDUIT
(AS REQUIRED)