Supervisor 2000 Installation Instructions
Page 10
For Assistance: [email protected] +1 (909) 591-8431 PUD1601R6-1
Seal the floor area around the conduits running up and
into the cabinets. This will prevent condensation and
debris build-up coming from whatever may be below
the floor.
Electrical Requirements
Conduit Requirements
Power Supply
110-120 VAC, 60 Hz or 220/240 VAC, 50 Hz
Power Requirements
Peak power consumption is 60W per lane with all options installed.
Operational Voltage
Primary power is stepped down and rectified for low-voltage12 VDC and 5 VDC
operation.
Fuse
2.5A (slo-blo) located in the master cabinet
Surge Protection
Alvarado suggests the use of surge protection on the high-voltage power line to
further protect electronics
NOTE
The conduit openings for each cabinet are
8" x 2.80” (203mm x 71mm). The three required conduits
will fit in these areas [Figure 7].
Primary Power
•
3/4” (19mm) power conduit for primary source
power (e.g. 120 VAC, 220 VAC) must be run to
the master and center cabinets.
Access Control/Readers/Ethernet
•
3/4” (19mm) conduit for external access control/
network communication must be run to all
cabinets requiring a card reader. Networked
turnstiles must have Ethernet cable run to the
master and center cabinets.
Crossover Cable
•
1 1/2” (38mm) conduit
must
be run to
interconnect the cabinets in each lane.
NOTE
Slave
Cabinet
Master
Cabinet
Conduit Openings
Figure 7
For multi-lane conduit requirements, refer to Appendix
A on Page 32.
NOTE
Symbology
Description
Conduit Size
Primary
Power
3/4”
Access Control/
Readers/
Ethernet
3/4”
Crossover
Cable
1.5”