Gutter Installation (Optional)
17
Now fit the gutter outlet to the
building, the centerline of the
downpipe should be in line with
the centerline of the end cloaking
trim (diagram 81). Fix the gutter
outlet to the building with a 40mm
Pan head screw. Fix another gutter
bracket half way between the
outlet and the gutter joint.
Measure the distance between the
gutter joint and the outlet then
trim the gutter section to fit, this
can then be inserted.
Diagram 80
Diagram 81
Diagram 82
02-2
515
B
02-251
7B
02-2529B
02-2507B
02-2507B
02-2514B
Next remove one of the cloaking
trim screws, the 3rd up from the
bottom works well. Take the
downpipe bracket and fix it with
this screw (diagram 82). Slot the
downpipe through the bracket and
on to the gutter outlet. You can
then tighten the round head bolt in
the downpipe bracket to secure it.
Finally, add the downpipe shoe.