Chapter 6
System Start-Up
Start Up Process
Once the procedures for power distribution tests have been successfully
completed, the controller is ready for installation of its modules and its second
power up. The installation process should be completed in the following order:
1. Switch off power to the controller — both field power and controller
power sources.
2. Make a record of the module and base unit serial numbers for future
reference.
3. Reinstate the power.
4. Install the modules in the following sequence.
5. Install the program enable key to the connector labeled KEY on the
processor base unit.
6. Install the first Processor module.
• Refer to the Processor Module start-up process.
7. Install the second or the third processor module (if required).
• Refer to the Processor Module start-up process.
8. Install the I/O modules.
• Refer to the I/O Module start up process.
9. Check system status indications show the system is on-line and
operating as expected.
System Configuration and Application Programming
When the hardware is installed and running you need to set up the system
configuration using the AADvance Workbench:
• For Workbench 1.x refer to the AADvance Configuration Guide Doc
No
ICSTT-RM405
for the detailed instructions on configuring a
system.
• For Workbench 2.x refer to the AADvance Configuration Guide Doc
No
ICSTT-RM458
for the detailed instructions on configuring a
system.
Содержание AADvance
Страница 4: ...4 Rockwell Automation PublicationICSTT RM448J EN P April 2018...
Страница 6: ...6 Rockwell Automation PublicationICSTT RM448J EN P April 2018 Summary of Changes...
Страница 14: ...14 Rockwell Automation PublicationICSTT RM448J EN P April 2018 Chapter 1 The AADvance System...
Страница 62: ...62 Rockwell Automation PublicationICSTT RM448J EN P April 2018 Chapter 2 The AADvanceSafety Controller...
Страница 66: ...66 Rockwell Automation PublicationICSTT RM448J EN P April 2018 Chapter 3 Application Resource Development...
Страница 132: ...132 Rockwell Automation PublicationICSTT RM448J EN P April 2018 Chapter 5 Install the AADvance System...
Страница 150: ...150 Rockwell Automation PublicationICSTT RM448J EN P April 2018 Chapter 8 Dismantling the AADvance System...