GUID-CF7095A1-76B7-490D-84C9-8DF11DEF62C9 V1 EN
Figure 25:
Setup complete
To cancel the insertion, click
Cancel
.
If an error is found on the
Setup Complete Page
, it is not
possible to go back and make modifications. If an error is
detected, cancel the insertion by clicking
Cancel
and insert the
IED again.
10. From the
Plant structure
view, check that PCM600 has turned online the IED
that was inserted to the bay level.
Data cannot be scanned from the protection relay and
proceeding is prevented if the IED is not online or if the IP
address is not correct.
4.3.2
Inserting an IED in offline mode
When the protection relay is not available or is not connected to PCM600, engineering
can be done offline. The offline configuration in PCM600 can be written to the
protection relay later when it is connected.