2.3
Workflow
Start
Project
SMT
PST
Modbus
IEC 61850
IEC 61850
Configuration Tool
Export
SCD
IET 600
Import
SCD
SMT
IED
WRITE
Start
CMT
Export SCL files
From PCM600
Import SCL file to
IET 600 and to
Signal engineering
Export updated
SCL files from IET 600
Import SCL file to
IET 600 and to
Signal engineering
Make GOOSE connections
Write configuration to IED
Create plant structure and
Insert IED objects
Configure IED functionality
Parameterization
Signal engineering
GUID-DF541272-FEDD-4FF1-8003-AF7EA66D594F V1 EN
Figure 3:
Protection relay engineering workflow proposal based on practical
experience and dependencies of the steps
It is possible to follow a different sequence based on the information available at the
time when the project is started. This means that several iterations may be needed to
complete the project.
Setting up a PCM600 project
•
The plant structure is built according to the substation structure.
The maximum size of a project is 180 IEDs. However, in order to
maintain good performance and usability of the tool, it is
Section 2
1MRS241255 B
Relay engineering process
16
611 series
Engineering Manual