Overview
Chapter 11
Verifying the internal configuration
1
Overview
Before start of this process, all individual devices that are involved in the fault clearance
process must have been tested as individuals and set in operation. The breaker must be
ready for an open-close-open cycle.
The shaping of the test process is dependent on the complexity of the design of the
switchyard. Hereby follows some items which could be used as guidelines.
Содержание REL 505-C1 2.3 Series
Страница 16: ...10 Note signs Chapter 2 Safety information ...
Страница 40: ...34 Checking the binary I O circuits Chapter 6 Checking the external circuitry ...
Страница 110: ...104 Two step time delayed phase overcurrent protection TOC2 Chapter 10 Verifying settings by secondary injection ...
Страница 114: ...108 Testing the interaction of the distance protection Chapter 11 Verifying the internal configuration ...