COMMISSIONING
PRODUCT
PCS6000
DOCUMENT KIND
User manual
DOCUMENT ID.
3BHS600000 E40
REV.
G
LANG.
en
PAGE
7.6.6. Insulation test checklist
1) Insulation of the cables to input transformer, from input transformer to converter
and from converter to motor is tested, and measured values within required
limits.
2) Test report is available.
If the commissioning personnel carry out the test, an additional day must be
reserved. After the test, the mains cables can be connected, except at the
converter end. Test must comply with the specification.
7.6.7. Power checklist
1) Medium voltage available for startup of converter.
2) Low voltage is available for startup of converter.
7.6.8. Miscellaneous checklist
1) Sufficient number and correct type of spare parts available.
2) Sufficient quantity of deionized water according is available. (see “Appendix C –
Mechanical drawings”).
3) A health and safety plan is created and available. Site specific introduction, if
required, is planned and will be provided to the commissioning personnel prior to
starting the commissioning.
4) Working tools and the required measurement equipment are available.
5) All required documents are received, read and understood
• Mechanical and electrical interface description
• Control interface description
• Communication link specification
• Transformer specification
• Electrical circuit diagram
• Grid breaker specification
• External cooling circuit requirements