Validation procedure
You must do the validation test using the checklist given in this manual
and the validation test plan of the complete safety system:
• at the initial start-up of the safety function
• after changes related to the safety function (wiring, components,
safety function -related parameter settings, etc.)
• after maintenance work related to the safety function
• at the proof test of the safety function.
The validation test must include at least the following steps:
• you must have a validation test plan
• you must test all commissioned functions for proper operation,
from each operation location
• you must document all validation tests
• you must sign and store the validation test report for further
reference.
■
Validation test reports
You must store the signed validation test reports in the logbook of
the machine and in the explosion protection document under the
scope of the ATEX User Directive 1999/92/EC or The Dangerous
Substances and Explosive Atmospheres Regulations 2002 (UK). The
report must include, as required by the referred standards:
• a description of the safety application (including a figure)
• a description and revisions of safety components that are used
in the safety application
• a list of all safety functions that are used in the safety application
• a list of all safety-related parameters and their values
44 Start-up and validation test
31
Содержание CPTC-02
Страница 2: ......
Страница 4: ......
Страница 20: ...20 ...
Страница 26: ...26 ...
Страница 32: ...32 ...
Страница 50: ...50 ...
Страница 54: ...54 ...
Страница 71: ...Technical data 71 ...
Страница 72: ...72 Technical data ...
Страница 73: ...Technical data 73 ...