Running the Group 2 Tests
Run the Group 2 tests to check the integrity of the
on-board circuitry and the on-board transceiver and cable
connectors. To run the External Loopback Test, you must
use a loopback plug.
CAUTION:
Do not run the External Loopback Test when
the 3C985B-SX server NIC is cabled to another device.
To run the Group 2 tests:
1 Insert the loopback plug into the 3C985B-SX
server NIC.
For instructions on constructing a loopback plug, see
Constructing Loopback Plugs
in this chapter.
2 From the
Select
menu on the diagnostics program
main screen, select the 3C985B-SX server NIC to
be tested.
3 From the
Test
menu, select
Test Setup
.
The Test Setup screen appears.
4 Disable Group 1 tests by selecting
Group 1
and
clicking
Disable Group
.
5 Verify that Group 3 tests are disabled.
If the Group 3 tests are not disabled, select
Group 3
, and
select
Disable Group
.
6 Select
Group 2
and select
Enable Group
.
You can enable and disable an individual test by selecting
the test and pressing the spacebar.
7 Enter the number of times you want the tests to run,
or select
Continuous
.
8 Click
OK.
The main screen reappears.
9 From the
Test
menu, select
Run Tests
.
The Test Results screen appears.
10 Click
Start
to run the Group 2 tests.
The test results are updated on the screen as the tests run.
11 When you are finished, remove the loopback plug
and reinsert the network cable.
Book Page 76 Monday, June 7, 1999 2:14 PM
Содержание EtherLink 3C985B-SX
Страница 1: ......
Страница 9: ......
Страница 15: ......
Страница 26: ...Creating a Load Balancing RSL and VLAN Configuration 25 Figure 4 Creating a Load Balancing RSL Group ...
Страница 29: ...28 CHAPTER 3 INSTALLING AND CONFIGURING THE WINDOWS NT DRIVER Figure 6 Creating a VLAN ...
Страница 91: ......
Страница 107: ......
Страница 113: ......