Chapter 8 Installation of Internal Power Cables and Grounding Cables
c.
In accordance with the label on each power cable, connect each end of the four
pairs of power cables to the corresponding connection terminal of the
modules. Tighten the screws.
d.
Install the protective cover for each
module, and tighten the screws.
Figure 8-3 Installing Power Cables for the E4140 Shelf
1.
Unified PDU
2.
Cable tray
3.
E4140 shelf
4.
Vertical cable tray
5.
Protective cover
6.
Horizontal cable tray
4.
Bind power cables that are routed along the horizontal cable tray, vertical cable tray,
and cable trays.
– End of Steps –